⚡ NEC Quick Hit: Schedule 40 PVC & HDPE Conduit ⚡

 The most common plastic raceways on the job! Schedule 40 PVC (Article 352) and HDPE (Article 353) share identical Chapter 9 dimensions. Let's break down the numbers from 1/2" to 6" 👇

SLIDE 2 (SMALLER TRADE SIZES) Small Sch 40 & HDPE Trade Sizes:

SLIDE 3 (MEDIUM TO LARGE SIZES) Medium to Large Sizes (40% Fill Limit):

⚠️ Note: Just like PVC, 3/8" trade size is skipped—standard runs start at 1/2".

SLIDE 4 (WRAP-UP) 💡 Apprentice Pro-Tip: 

Because Articles 352 and 353 map to the same Chapter 9 table, whether you're pulling underground HDPE or running Sch 40 PVC stub-ups, your fill calculations stay completely consistent!

💬 Save this post for your next underground trench or slab rough-in! 🔗 More code breakdowns & study tools at www.JoshTheSparky.com