SLIDE 1 (HOOK / COVER) ⚡ NEC Quick Hit: Sheath Grounding & Antennas (Part 2 - Article 750) ⚡
How do you properly ground metallic cable sheaths, coaxial shields, and roof antennas entering a building? Part II of Article 750 lays down the law. Let's break it down! 👇
SLIDE 2 (BUILDING ENTRANCE SHEATH GROUNDING) Protecting Cable Entries:
Communication & Coaxial Shields: Metal sheath members and outer conductive shields of coaxial cables must be grounded or bonded as close as practicable to the point of entrance (or terminated outside).
Alternative Interruption: Metal sheaths can alternatively be interrupted by an insulating joint or equivalent device.
SLIDE 3 (ANTENNA MASTS & LEAD-IN PROTECTORS) Mast Grounding & Rolling Spheres:
Masts & Structures: Metal structures supporting antennas must be grounded or bonded unless the antenna falls completely within a protective zone defined by a 46 m (150 ft) radius rolling sphere.
Lead-In Protectors: Antenna surge protectors must be connected between conductors and grounded shields using approved grounding conductors.
SLIDE 4 (WRAP-UP) 💡 Apprentice Pro-Tip:
Placing your sheath grounding blocks and primary protectors as close as practicable to the point of building entrance dramatically shortens bonding paths and prevents dangerous potential differences during lightning strikes!
💬 Save this post for your next telecom or antenna rough-in! 🔗
More code breakdowns at www.JoshTheSparky.com