Slide 1 — Hook "Quick episode — how the disconnect's rating and the feeder/branch-circuit conductors themselves get sized."
Slide 2 — 267.39 Rating of the disconnect
Transformers only: disconnect rating ≥ sum of the transformers' nameplate ratings.
Transformers + utilization equipment: disconnect rating ≥ transformer nameplate sum + 100% of the utilization equipment's simultaneous designed load.
Supervised installations: qualified persons under engineering supervision can determine the rating — but it still can't be less than the size of the feeder/branch circuit supplying that disconnect.
Slide 3 — 267.40 Conductor sizing
This section doesn't reinvent the wheel — it just points you to the right place: branch-circuit conductor sizing follows 265.19 (the medium-voltage branch circuits article), and feeder conductor sizing follows 266.4 (the medium-voltage feeders article).
Slide 4 — Quiz + CTA Q: "Under a supervised installation, can the disconnect rating ever be smaller than the feeder/branch circuit it's connected to?" A) Yes, if an engineer approves it B) No — it can never be smaller than the supplying feeder/branch circuit C) Only for transformer-only loads D) There's no minimum in supervised installations
✅ Answer: B — 267.39(C): even under engineering supervision, the rating floor is the feeder/branch-circuit size.
CTA: Follow for more daily quick-hit study notes 📚⚡